S.No. | Project Name | Project Details | Cost of Projects (In Lacs) | Work Starting Date | Expected Completion Date | Benifits to People | Photographs |
---|---|---|---|---|---|---|---|
1 | Construction of EWS & LIG Flats (G+3) under CMJAY-2015 at Sector A (R-1), South Extension Scheme, Udaipur. | Project under CMJAY-2015 provision 4(A)(i), 160 EWS & 128 LIG flats total 288 (G+3) are being constructed on total plot area for EWS/LIG of 0.75 Hectare. Developer is M/s NILA Infrastructure Ltd. of Ahmedabad. | 929.16 | 30-06-2016 | 29-06-2019 | Providing flats at subsidized rates to persons not having their own plots/houses in Rajasthan, giving them opportunity to live in a fully developed society will all infrastructure facilities like roads, electricity, parks, community centers etc. and extending to them the benefits of central subsidy available under Prime Minister Awas Yojana (PMAY) | |
2 | Construction of EWS & LIG Flats (G+3) under CMJAY-2015 at Sector A (R-2), South Extension Scheme, Udaipur. | Project under CMJAY-2015 provision 4(A)(i), 160 EWS & 128 LIG flats total 288 (G+3) are being constructed on total plot area for EWS/LIG of 0.75 Hectare. Developer is M/s NILA Infrastructure Ltd. of Ahmedabad. |
1075.32 |
30-06-2016 |
29-06-2019 |
As Above | |
3 | Construction of EWS & LIG Flats (G+3) under CMJAY-2015 at Sector A (R-3), South Extension Scheme, Udaipur. | Project under CMJAY-2015 provision 4(A)(i), 160 EWS & 128 LIG flats total 288 (G+3) are being constructed on total plot area for EWS/LIG of 0.75 Hectare. Developer is M/s NILA Infrastructure Ltd. of Ahmedabad. |
1054.44 |
30-06-2016 |
29-06-2019 |
As Above | |
4 | Construction of EWS & LIG Flats (G+3) under CMJAY-2015 at Sector A (R-4), South Extension Scheme, Udaipur. | Project under CMJAY-2015 provision 4(A)(i), 160 EWS & 128 LIG flats total 288 (G+3) are being constructed on total plot area for EWS/LIG of 0.75 Hectare. Developer is M/s NILA Infrastructure Ltd. of Ahmedabad. |
929.16 |
30-06-2016 |
29-06-2019 |
As Above | |
5 | Construction of EWS & LIG Flats (G+3) under CMJAY-2015 at Pannadhay Nagar (R-5), South Extension Scheme, Udaipur. | Project under CMJAY-2015 provision 4(A)(i), 448 EWS & 128 LIG flats total 576 (G+3) are being constructed on total plot area for EWS/LIG of 1.5 Hectare. Developer is M/s Rhythm Infrastructures Pvt. Ltd. of Ahmedabad. |
1868.00 |
22-03-2017 |
21-09-2020 |
As Above | |
6 | Construction of 1696 (EWS-848, LIG-584, MIG-A 264) Flats at Mega Awas Yojana Dholi Magri Bedwas. | Work of 1696 flats is under speedy progress in 8.00 Hectare scheme area and is likely to be completed within the prescribe timeline i.e. 09-04-2019. Allotments of all the plots have been done by Lottery. |
6695.00 |
11-02-2015 |
09-04-2019 |
Providing flats to the shelter less people at low cost price in a fully developed schemes having all basic utilities services. |
|
7 | Construction of 480 Nos. EWS flats (G+3) Under Affordable Housing Scheme at Revenue Village Satodi Magri, Bedwas. | Work of 480 EWS flats is under speedy progress in 1.8 Hectare scheme area and is likely to be completed within the prescribe timeline i.e. 29-07-2018. Allotments of all the plots have been done by Lottery. |
1625.00 |
25-01-2017 |
29-07-2018 |
Providing flats to the shelter less people at low cost price in a fully developed schemes having all basic utilities services. |
|
8 | Widening of existing 2-Lane N.H. 8 highway Road from Pratap Nagar Chouraha to Balicha Tiraha, Udaipur. | Widening of existing two lane NH.8 Bypass from 7.5 Mtr. carriage way width to 12.0 mtr. in 11.5 Km. length is under progress and is likely to be completed by scheduled date i.e. 31-08-2018. |
1900.00 |
01-09-2017 |
31-08-2018 |
People will be benefited by frequent traffic jam and will also lower down the accidental chances due to high intensity of heavy commercial vehicles plying on this road. |
|
9 | Construction of Link Road From Udaipole Bus Stand to Chittorgarh Road, Udaipur. | It is an important 60 feet wide Master Plan road link in 800 mtr. length connecting Roadways Bus Stand Udaipur to Chittorgarh Road. |
229.85 |
28-04-2017 |
30-06-2018 |
This road will not only serve as shortest link for habitation residing in Sector area to Roadways Bus Stand but will also help in de-congestion of traffic at Udaipole and Surajpole Circle. |
|
10 | Construction of Underpass at Eklingpura Junction of N.H. 8 bypass Pratapnagar – Balicha, Udaipur. | The Underpass at Eklingpura Junction across NH.8 Bypass has been proposed with two box cells with 5.50 mtr. width and 4.50 mtr. height and 30.00 mtr. in length with approaches in 150.00 mtr. length on either side i.e. towards Udaipur City and towards Umarda. |
752.00 |
24-08-2017 |
23-08-2018 |
Eklilngpura Junction being the busiest junction with high intensity of heavy traffic crossing from either sides, after construction of Underpass will not only reduce frequent long traffic jam but will also help to make this junction accidental free zone which is at present among one of the identified black spots in Udaipur. |
|
11 | Construction of 304 Nos. EWS (G+3) Flats at Dangiyon Ki Pancholi, Bedwas, Udaipur under Chief Minister Jan Awas Yojana. | The proposed site is at Khasra no. 2 at Dangiyo ki Pancholi, Bedwas with area 1.4 Hectare is only 250.00 mtrs. from NH.76 and is in vicinity of habitated colony. |
1260.00 |
21-03-2018 |
20-03-2020 |
This flats will cater the need of E.W.S. beneficiaries selected under demand survey of PMAY. |
|
12 | Construction of basement Parking on vacant land of S.I.E.R.T. Hostel, Fatehsagar, Dewali end. | Present working area is 2300.00 sqmt. on which 134 Nos. Cars & 72 Nos. Two Wheelers can be parked. |
285.00 |
17-09-2016 |
31-07-2018 |
This parking will reduce the heavy traffic jam on Fatehsagar road which is one of the major tourist area in Udaipur. It will also reduce accidents due to uneven parking on road and provide safety to vehicles from theft. |